Search

Search bills, members, committees and pages...

H.R. 2986

U.S. HouseIn House Committee

Summary

H.R. 2986, the Expediting Generator Interconnection Procedures Act of 2025, was introduced in the House on Apr 24, 2025 by Rep. Kathy Castor (D) with 1 co-sponsor. It last saw action on Jun 24, 2026: Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.


Record

Text

H.R. 2986 has 1 co-sponsor.

hb2986/introduced-in-house.txt
119 HR 2986 IH: Expediting Generator Interconnection Procedures Act of 2025
U.S. House of Representatives
2025-04-24
text/xml
EN
Pursuant to Title 17 Section 105 of the United States Code, this file is not subject to copyright protection and is in the public domain.
I 119th CONGRESS 1st Session H. R. 2986 IN THE HOUSE OF REPRESENTATIVES April 24, 2025 Ms. Castor of Florida introduced the following bill; which was referred to the Committee on Energy and Commerce A BILL
To require the Federal Energy Regulatory Commission to promulgate regulations that accelerate the interconnection of electric generation and storage resources to the transmission system through more efficient and effective interconnection procedures.
1.
Short title
This Act may be cited as the Expediting Generator Interconnection Procedures Act of 2025 .
2.
Definitions
In this Act:
(1)
Commission
The term Commission means the Federal Energy Regulatory Commission.
(2)
Energy storage project
The term energy storage project means—
(A)
any equipment that receives, stores, and delivers energy using batteries, compressed air, pumped hydropower, hydrogen storage (including hydrolysis), thermal energy storage, regenerative fuel cells, flywheels, capacitors, superconducting magnets, or other technologies identified by the Commission; and
(B)
any project for the construction or modification of equipment described in subparagraph (A) as part of an effort to build-out transmission interconnection opportunities.
(3)
Generation project
The term generation project means—
(A)
any facility—
(i)
that generates or injects electricity; and
(ii)
for which an interconnection request is subject to the jurisdiction of the Commission; and
(B)
any project for the construction or modification of a facility described in subparagraph (A).
(4)
Interconnection customer
The term interconnection customer means a person or entity that has submitted an interconnection request.
(5)
Interconnection request
The term interconnection request means a request submitted to a public utility to interconnect a new generation project or energy storage project to the electric system of a public utility for the purposes of transmission of electric energy in interstate commerce or the sale of electric energy at wholesale.
(6)
Public utility
The term public utility has the meaning given the term in section 201(e) of the Federal Power Act ( 16 U.S.C. 824(e) ).
(7)
Transmission facility
The term transmission facility means a facility that is used for the transmission of electric energy in interstate commerce.
(8)
Transmission provider
The term transmission provider means a public utility that owns, operates, or controls 1 or more transmission facilities.
(9)
Transmission system
The term transmission system means a network of transmission facilities used for the transmission of electric energy in interstate commerce.
3.
Rulemaking to expedite generator interconnection procedures
(a)
In general
Not later than 180 days after the date of enactment of this Act, the Commission shall initiate a rulemaking—
(1)
to address the inefficiencies and ineffectiveness of existing procedures for processing interconnection requests to ensure that new generation projects and energy storage projects can interconnect quickly, cost-effectively, and reliably; and
(2)
to revise the pro forma Large Generator Interconnection Procedures and, as appropriate, the pro forma Large Generator Interconnection Agreement, promulgated pursuant to section 35.28(f) of title 18, Code of Federal Regulations (or successor regulations), to require transmission providers—
(A)
to develop and employ modeling assumptions for each resource type based on actual operating abilities and practices, for the purposes of studying an interconnection request;
(B)
to study interconnection requests in a manner consistent with the risk tolerance of the interconnection customer;
(C)
to select, as appropriate, 1 or more cost-effective solutions to address network reliability needs that may be identified while studying an interconnection request;
(D)
to provide sufficient information to interconnection customers for the interconnection customers to understand how a transmission provider has implemented the assumptions and solutions described in subparagraphs (A) and (C);
(E)
to share and employ, as appropriate, queue management best practices, including with respect to the use of advanced computing technologies, automation, and standardized study criteria, in evaluating interconnection requests, in order to expedite study results; and
(F)
to implement transparency and performance-enhancing measures to ensure timely and cost-conscious construction of necessary network upgrades once an interconnection agreement has been executed.
(b)
Deadline for final rule
Not later than 18 months after the date of enactment of this Act, the Commission shall promulgate a final rule to complete the rulemaking initiated under subsection (a).
(c)
Savings clause
Nothing in this section alters, or may be construed to alter, the allocation of costs of the transmission system pursuant to the ratemaking authority of the Commission under section 205 of the Federal Power Act ( 16 U.S.C. 824d ).

Tracker

The tracker indicates the progress of this legislation as it moves through the legislative process.

  1. Introduced2025-04-24
  2. Passed House
  3. Passed Senate
  4. Conference
  5. To President
  6. Became Law

To require the Federal Energy Regulatory Commission to promulgate regulations that accelerate the interconnection of electric generation and storage resources to the transmission system through more efficient and effective interconnection procedures.

Sponsors

Rep. Kathy Castor (D) sponsors H.R. 2986, and 1 member has co-sponsored it.

Committees

H.R. 2986 went before 2 committees: Energy Subcommittee and Energy and Commerce.

Energy Subcommittee
Energy Subcommittee
Reported by · Jun 24, 2026
Energy and Commerce
Energy and Commerce
Referred To · Apr 24, 2025 · 1,636 Bills

Actions

H.R. 2986 has taken 5 actions since Apr 24, 2025, the latest on Jun 24, 2026.

ChamberAction
Jun 24, 2026
House
Subcommittee Consideration and Mark-up Session HeldEnergy Subcommittee
Jun 24, 2026
House
Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.Energy Subcommittee
Apr 24, 2026
House
Referred to the Subcommittee on Energy.Energy Subcommittee
Apr 24, 2025
House
Introduced in House
Apr 24, 2025
House
Referred to the House Committee on Energy and Commerce.Energy and Commerce Committee

Votes

H.R. 2986 has not gone to a roll call.

Titles

H.R. 2986 goes by 3 titles, 1 of them short titles.

  • Expediting Generator Interconnection Procedures Act of 2025 — Display Title
  • Expediting Generator Interconnection Procedures Act of 2025 — Short Title(s) as Introduced
  • To require the Federal Energy Regulatory Commission to promulgate regulations that accelerate the interconnection of electric generation and storage resources to the transmission system through more efficient and effective interconnection procedures. — Official Title as Introduced

Lobbying

3 clients hired 3 firms and 111 registered lobbyists who named H.R. 2986 in 15 quarterly filings, 2025 to 2026. Reported under the Lobbying Disclosure Act; a filing’s income covers everything its registrant worked that quarter, so the amounts below are the filings’, not this bill’s.

Filed under Energy/Nuclear, Budget/Appropriations, Taxation/Internal Revenue Code, Trade (domestic/foreign), Government Issues, Aerospace, Automotive Industry, Aviation/Airlines/Airports.

Clients

Who paid to be heard, by how many filings named the bill.

ClientBusinessStateFirmsFilingsReported
CHAMBER OF COMMERCE OF THE U.S.A.District of Columbia16
OHIO MUNICIPAL ELECTRIC ASSOCIATIONOhio15
CORPORATE ENERGY BUYERS ASSOCIATIONDistrict of Columbia14

Firms

Registrants who filed on the bill, by filings.

Lobbyists

Named on the filings that cite the bill. The 20 named most often, of 111.

Filings

The documents themselves, on the Senate’s Lobbying Disclosure site, largest reported first.

ClientRegistrantPeriodReportedDocument
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2026 first_quarter$19.8M1st Quarter - Amendme…
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2026 first_quarter$19.8M1st Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2025 second_quarter$19.3M2nd Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2025 fourth_quarter$18M4th Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2026 second_quarter$17M2nd Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2025 third_quarter$13.7M3rd Quarter - Report
CORPORATE ENERGY BUYERS ASSOCIATIONCORPORATE ENERGY BUYERS ASSOCIATION2025 third_quarter$370K3rd Quarter - Report
CORPORATE ENERGY BUYERS ASSOCIATIONCORPORATE ENERGY BUYERS ASSOCIATION2025 fourth_quarter$210K4th Quarter - Report
CORPORATE ENERGY BUYERS ASSOCIATIONCORPORATE ENERGY BUYERS ASSOCIATION2026 first_quarter$200K1st Quarter - Report
CORPORATE ENERGY BUYERS ASSOCIATIONCORPORATE ENERGY BUYERS ASSOCIATION2025 second_quarter$140K2nd Quarter - Report
OHIO MUNICIPAL ELECTRIC ASSOCIATIONOHIO MUNICIPAL ELECTRIC ASSOCIATION2026 second_quarter$70K2nd Quarter - Report
OHIO MUNICIPAL ELECTRIC ASSOCIATIONOHIO MUNICIPAL ELECTRIC ASSOCIATION2026 first_quarter$70K1st Quarter - Report
OHIO MUNICIPAL ELECTRIC ASSOCIATIONOHIO MUNICIPAL ELECTRIC ASSOCIATION2025 fourth_quarter$70K4th Quarter - Report
OHIO MUNICIPAL ELECTRIC ASSOCIATIONOHIO MUNICIPAL ELECTRIC ASSOCIATION2025 third_quarter$70K3rd Quarter - Report
OHIO MUNICIPAL ELECTRIC ASSOCIATIONOHIO MUNICIPAL ELECTRIC ASSOCIATION2025 second_quarter$70K2nd Quarter - Report

Classification

The Congressional Research Service files H.R. 2986 under Energy, one of its 31 policy areas, and gives it 5 legislative subjects.

CRS Subjects

CRS assigns every bill one policy area from its 31; H.R. 2986’s is Energy.

hr2986/policy-areas.txt
EnergyAgriculture and FoodAnimalsArmed Forces and National SecurityArts, Culture, ReligionCivil Rights and Liberties, Minority IssuesCommerceCongressCrime and Law EnforcementEconomics and Public FinanceEducationEmergency ManagementEnvironmental ProtectionFamiliesFinance and Financial SectorForeign Trade and International FinanceGovernment Operations and PoliticsHealthHousing and Community DevelopmentImmigrationInternational AffairsLabor and EmploymentLawNative AmericansPublic Lands and Natural ResourcesScience, Technology, CommunicationsSocial WelfareSports and RecreationTaxationTransportation and Public WorksWater Resources Development

Legislative Subjects

H.R. 2986 carries 5 of CRS’s legislative subjects, from Electric power generation and transmission to Public utilities and utility rates.

hr2986/subjects.txt
Electric power generation and transmissionEnergy efficiency and conservationEnergy storage, supplies, demandInfrastructure developmentPublic utilities and utility rates

Constitutional authority

The clause the sponsor cites as Congress’s power to enact H.R. 2986, as entered in the Congressional Record.

[Congressional Record Volume 171, Number 69 (Thursday, April 24, 2025)][House]From the Congressional Record Online through the Government Publishing Office [www.gpo.gov]By Ms. CASTOR of Florida:H.R. 2986.Congress has the power to enact this legislation pursuantto the following:Article I, Section 8, Clause 1 of the Constitutio providesCongress with the authority to ``provide for the commonDefense and general Welfare'' of Americans.[Page H1624]

Source: congress.gov · legiscan.com