H.R. 3668, the Improving Interagency Coordination for Pipeline Reviews Act, was introduced in the House on Jun 2, 2025 by Rep. Richard Hudson (R) with 3 co-sponsors. It was referred to Commerce, Science, And Transportation, and last saw action on Dec 15, 2025: Received in the Senate and Read twice and referred to the Committee on Commerce, Science, and Transportation.


Record

Text

H.R. 3668 has 3 co-sponsors and 2 roll calls.

hb3668/engrossed-in-house.txt
119 HR 3668 EH: Improving Interagency Coordination for Pipeline Reviews Act
U.S. House of Representatives
text/xml
EN
Pursuant to Title 17 Section 105 of the United States Code, this file is not subject to copyright protection and is in the public domain.
IB
119th CONGRESS 1st Session
H. R. 3668
IN THE HOUSE OF REPRESENTATIVES
AN ACT
To promote interagency coordination for reviewing certain authorizations under section 3 of the Natural Gas Act, and for other purposes.
1.
Short title
This Act may be cited as the Improving Interagency Coordination for Pipeline Reviews Act .
2.
Promoting interagency coordination for review of natural gas pipelines
(a)
Definitions
In this section:
(1)
Commission
The term Commission means the Federal Energy Regulatory Commission.
(2)
Federal authorization
The term Federal authorization has the meaning given that term in section 15(a) of the Natural Gas Act ( 15 U.S.C. 717n(a) ).
(3)
NEPA review
The term NEPA review means the process of reviewing a proposed Federal action under section 102 of the National Environmental Policy Act of 1969 ( 42 U.S.C. 4332 ).
(4)
Project-related NEPA review
The term project-related NEPA review means any NEPA review required to be conducted with respect to the issuance of an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act.
(b)
Commission NEPA review responsibilities
In acting as the lead agency under section 15(b)(1) of the Natural Gas Act for the purposes of complying with the National Environmental Policy Act of 1969 ( 42 U.S.C. 4321 et seq. ) with respect to an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act, the Commission shall, in accordance with this section and other applicable Federal law—
(1)
be the only lead agency;
(2)
coordinate as early as practicable with each agency designated as a participating agency under subsection (d)(3) to ensure that the Commission develops information in conducting its project-related NEPA review that is usable by the participating agency in considering an aspect of an application for a Federal authorization for which the agency is responsible; and
(3)
take such actions as are necessary and proper to facilitate the expeditious resolution of its project-related NEPA review.
(c)
Deference to Commission
In making a decision with respect to a Federal authorization required with respect to an application for authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act, each agency shall give deference, to the maximum extent authorized by law, to the scope of the project-related NEPA review that the Commission determines to be appropriate.
(d)
Participating agencies
(1)
Identification
The Commission shall identify, not later than 30 days after the Commission receives an application for an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act, any Federal or State agency, local government, or Indian Tribe that may issue a Federal authorization or is required by Federal law to consult with the Commission in conjunction with the issuance of a Federal authorization required for such authorization or certificate.
(2)
Invitation
(A)
In general
Not later than 45 days after the Commission receives an application for an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act, the Commission shall invite any agency identified under paragraph (1) to participate in the review process for the applicable Federal authorization.
(B)
Deadline
An invitation issued under subparagraph (A) shall establish a deadline by which a response to the invitation shall be submitted to the Commission, which may be extended by the Commission for good cause.
(3)
Designation as participating agencies
Not later than 60 days after the Commission receives an application for an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act, the Commission shall designate an agency identified under paragraph (1) as a participating agency with respect to an application for authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act unless the agency informs the Commission, in writing, by the deadline established pursuant to paragraph (2)(B), that the agency—
(A)
has no jurisdiction or authority with respect to the applicable Federal authorization;
(B)
has no special expertise or information relevant to any project-related NEPA review; or
(C)
does not intend to submit comments for the record for the project-related NEPA review conducted by the Commission.
(4)
Effect of non-designation
(A)
Effect on agency
Any agency that is not designated as a participating agency under paragraph (3) with respect to an application for an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act may not request or conduct a NEPA review that is supplemental to the project-related NEPA review conducted by the Commission, unless the agency—
(i)
demonstrates that such review is legally necessary for the agency to carry out responsibilities in considering an aspect of an application for a Federal authorization; and
(ii)
requires information that could not have been obtained during the project-related NEPA review conducted by the Commission.
(B)
Comments; record
The Commission shall not, with respect to an agency that is not designated as a participating agency under paragraph (3) with respect to an application for an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act—
(i)
consider any comments or other information submitted by such agency for the project-related NEPA review conducted by the Commission; or
(ii)
include any such comments or other information in the record for such project-related NEPA review.
(e)
Water quality impacts
(1)
In general
Notwithstanding section 401 of the Federal Water Pollution Control Act ( 33 U.S.C. 1341 ), an applicant for a Federal authorization shall not be required to provide a certification under such section with respect to the Federal authorization.
(2)
Coordination
With respect to any NEPA review for a Federal authorization to conduct an activity that will directly result in a discharge into the navigable waters (within the meaning of the Federal Water Pollution Control Act), the Commission shall identify as an agency under subsection (d)(1) the State in which the discharge originates or will originate, or, if appropriate, the interstate water pollution control agency having jurisdiction over the navigable waters at the point where the discharge originates or will originate.
(3)
Proposed conditions
A State or interstate agency designated as a participating agency pursuant to paragraph (2) may propose to the Commission terms or conditions for inclusion in an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act that the State or interstate agency determines are necessary to ensure that any activity described in paragraph (2) conducted pursuant to such authorization or certification will comply with the applicable provisions of sections 301, 302, 303, 306, and 307 of the Federal Water Pollution Control Act.
(4)
Commission consideration of conditions
The Commission may include a term or condition in an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act proposed by a State or interstate agency under paragraph (3) only if the Commission finds that the term or condition is necessary to ensure that any activity described in paragraph (2) conducted pursuant to such authorization or certification will comply with the applicable provisions of sections 301, 302, 303, 306, and 307 of the Federal Water Pollution Control Act.
(f)
Schedule
(1)
Deadline for Federal authorizations
A deadline for a Federal authorization required with respect to an application for authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act set by the Commission under section 15(c)(1) of such Act shall be not later than 90 days after the Commission completes its project-related NEPA review, unless an applicable schedule is otherwise established by Federal law.
(2)
Concurrent reviews
Each Federal and State agency—
(A)
that may consider an application for a Federal authorization required with respect to an application for authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act shall formulate and implement a plan for administrative, policy, and procedural mechanisms to enable the agency to ensure completion of Federal authorizations in compliance with schedules established by the Commission under section 15(c)(1) of such Act; and
(B)
in considering an aspect of an application for a Federal authorization required with respect to an application for authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act, shall—
(i)
formulate and implement a plan to enable the agency to comply with the schedule established by the Commission under section 15(c)(1) of such Act;
(ii)
carry out the obligations of that agency under applicable law concurrently, and in conjunction with, the project-related NEPA review conducted by the Commission, and in compliance with the schedule established by the Commission under section 15(c)(1) of such Act, unless the agency notifies the Commission in writing that doing so would impair the ability of the agency to conduct needed analysis or otherwise carry out such obligations;
(iii)
transmit to the Commission a statement—
(I)
acknowledging receipt of the schedule established by the Commission under section 15(c)(1) of the Natural Gas Act; and
(II)
setting forth the plan formulated under clause (i) of this subparagraph;
(iv)
not later than 30 days after the agency receives such application for a Federal authorization, transmit to the applicant a notice—
(I)
indicating whether such application is ready for processing; and
(II)
if such application is not ready for processing, that includes a comprehensive description of the information needed for the agency to determine that the application is ready for processing;
(v)
determine that such application for a Federal authorization is ready for processing for purposes of clause (iv) if such application is sufficiently complete for the purposes of commencing consideration, regardless of whether supplemental information is necessary to enable the agency to complete the consideration required by law with respect to such application; and
(vi)
not less often than once every 90 days, transmit to the Commission a report describing the progress made in considering such application for a Federal authorization.
(3)
Failure to meet deadline
If a Federal or State agency, including the Commission, fails to meet a deadline for a Federal authorization set forth in the schedule established by the Commission under section 15(c)(1) of the Natural Gas Act, not later than 5 days after such deadline, the head of the relevant Federal agency (including, in the case of a failure by a State agency, the Federal agency overseeing the delegated authority) shall notify Congress and the Commission of such failure and set forth a recommended implementation plan to ensure completion of the action to which such deadline applied.
(g)
Consideration of applications for Federal authorization
(1)
Issue identification and resolution
(A)
Identification
Federal and State agencies that may consider an aspect of an application for a Federal authorization shall identify, as early as possible, any issues of concern that may delay or prevent an agency from working with the Commission to resolve such issues and granting such authorization.
(B)
Issue resolution
The Commission may forward any issue of concern identified under subparagraph (A) to the heads of the relevant agencies (including, in the case of an issue of concern that is a failure by a State agency, the Federal agency overseeing the delegated authority, if applicable) for resolution.
(2)
Remote surveys
If a Federal or State agency considering an aspect of an application for a Federal authorization requires the person applying for such authorization to submit data, the agency shall consider any such data gathered by aerial or other remote means that the person submits. The agency may grant a conditional approval for the Federal authorization based on data gathered by aerial or remote means, conditioned on the verification of such data by subsequent onsite inspection.
(3)
Application processing
The Commission, and Federal and State agencies, may allow a person applying for a Federal authorization to fund a third-party contractor to assist in reviewing the application for such authorization.
(h)
Accountability, transparency, efficiency
For an application for an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act that requires multiple Federal authorizations, the Commission, with input from any Federal or State agency considering an aspect of the application, shall track and make available to the public on the Commission’s website information related to the actions required to complete the Federal authorizations. Such information shall include the following:
(1)
The schedule established by the Commission under section 15(c)(1) of the Natural Gas Act.
(2)
A list of all the actions required by each applicable agency to complete permitting, reviews, and other actions necessary to obtain a final decision on the application.
(3)
The expected completion date for each such action.
(4)
A point of contact at the agency responsible for each such action.
(5)
In the event that an action is still pending as of the expected date of completion, a brief explanation of the reasons for the delay.
(i)
Pipeline security
In considering an application for an authorization under section 3 of the Natural Gas Act or a certificate of public convenience and necessity under section 7 of such Act, the Federal Energy Regulatory Commission shall consult with the Administrator of the Transportation Security Administration regarding the applicant’s compliance with security guidance and best practice recommendations of the Administration regarding pipeline infrastructure security, pipeline cybersecurity, pipeline personnel security, and other pipeline security measures.
Passed the House of Representatives December 12, 2025. Kevin F. McCumber, Clerk.

Tracker

The tracker indicates the progress of this legislation as it moves through the legislative process.

  1. Introduced2025-06-02
  2. Passed House2025-12-12
  3. Passed Senate
  4. Conference
  5. To President
  6. Became Law

CRS Summary

The summaries are the Congressional Research Service’s, one per stage. Read them in full.

Reported to House Sep 15, 2025

hb3668/reported-to-house.md

Shown Here:
Reported to House (09/15/2025)

Improving Interagency Coordination for Pipeline Reviews Act

This bill expedites the environmental review of certain natural gas pipeline projects or liquefied natural gas (LNG) import or export terminals for authorizations under the Natural Gas Act.

Specifically, the bill makes the Federal Energy Regulatory Commission (FERC) the only lead agency for the purpose of coordinating the environmental review of such projects under the National Environmental Policy Act of 1969 (NEPA). Thus, agencies involved in the environmental review process must defer to FERC's approved scope for a NEPA review.

FERC must invite certain federal, state, local, or tribal governmental agencies to participate in the review process for an authorization and designate the applicable governments as participating agencies by deadlines established by the bill. In addition, FERC must consult with the Transportation Security Administration regarding various pipeline security measures.

The bill prohibits FERC from establishing a deadline for authorizing a project that is more than 90 days after the completion of the NEPA review. It also requires concurrent reviews when multiple federal or state agencies are involved.

Applicants for projects do not have to obtain a water quality certification from states under Section 401 of the Clean Water Act. FERC must coordinate its NEPA review with states where a potential discharge into navigable waters may occur.

If a federal or state agency requires an applicant for a pipeline authorization to submit data, the agency must consider any such data gathered by aerial or other remote means that is submitted.

Sponsors

Rep. Richard Hudson (R) sponsors H.R. 3668, and 3 members have co-sponsored it, 1 of them from the day it was introduced.

Committees

H.R. 3668 went before 4 committees: Commerce, Science, and Transportation, Energy and Commerce, Transportation and Infrastructure and Energy Subcommittee.

Commerce, Science, and Transportation
Commerce, Science, and Transportation
Referred To · Dec 15, 2025 · 458 Bills
Energy and Commerce
Energy and Commerce
Reported By · Nov 25, 2025 · 1,636 Bills
Transportation and Infrastructure
Transportation and Infrastructure
Discharged From · Sep 15, 2025 · 156 Bills
Energy Subcommittee
Energy Subcommittee
Reported by · Jun 5, 2025

Reports

2 committee reports have been filed on H.R. 3668, the latest H. Rept. 119-297,Part 1.

Actions

H.R. 3668 has taken 23 actions since Jun 2, 2025, the latest on Dec 15, 2025.

ChamberAction
Dec 15, 2025
Senate
Received in the Senate and Read twice and referred to the Committee on Commerce, Science, and Transportation.Commerce, Science, and Transportation Committee
Dec 12, 202509:12
House
Considered under the provisions of rule H. Res. 936. (consideration: CR H5814-5822)
Dec 12, 202509:12
House
Rule provides for consideration of H.R. 3898, H.R. 3383, H.R. 3638, H.R. 3628, H.R. 3668 and S. 1071. The resolution provides for consideration of H.R. 3898, H.R. 3383, H.R. 3638, and H.R. 3628 under a structured rule; and H.R. 3668 and S. 1071 under a closed rule. The resolution provides for one motion to recommit on H.R. 3898, H.R. 3383, H.R. 3638, H.R. 3628, and H.R. 3668; and one motion to commit on S. 1071.
Dec 12, 202509:13
House
DEBATE - The House proceeded with one hour of debate on H.R. 3668.
Dec 12, 202509:52
House
The previous question was ordered pursuant to the rule.

Votes

H.R. 3668 went to 2 roll calls in the House, the latest on Dec 12, 2025 at 213184.

ChamberQuestion
Yea
Nay
Dec 12, 2025
House
On Passage
213
184
Dec 12, 2025
House
On Motion to Recommit
194
204

1 bill is related to H.R. 3668.

Titles

H.R. 3668 goes by 7 titles, 4 of them short titles.

  • Improving Interagency Coordination for Pipeline Reviews Act — Short Titles from RFS (Referred to Senate) bill text
  • Improving Interagency Coordination for Pipeline Reviews Act — Short Title(s) as Passed House
  • To promote interagency coordination for reviewing certain authorizations under section 3 of the Natural Gas Act, and for other purposes. — Official Titles from EH (Engrossed in House) bill text
  • Improving Interagency Coordination for Pipeline Reviews Act — Short Title(s) as Reported to House
  • Improving Interagency Coordination for Pipeline Reviews Act — Display Title
  • Improving Interagency Coordination for Pipeline Reviews Act — Short Title(s) as Introduced
  • To promote interagency coordination for reviewing certain authorizations under section 3 of the Natural Gas Act, and for other purposes. — Official Title as Introduced

Cost estimate

The Congressional Budget Office has filed 1 estimate for H.R. 3668, the latest on Oct 23, 2025.


Lobbying

17 clients hired 16 firms and 168 registered lobbyists who named H.R. 3668 in 59 quarterly filings, 2025 to 2026. Reported under the Lobbying Disclosure Act; a filing’s income covers everything its registrant worked that quarter, so the amounts below are the filings’, not this bill’s.

Filed under Taxation/Internal Revenue Code, Energy/Nuclear, Budget/Appropriations, Environment/Superfund, Transportation, Homeland Security, Telecommunications, Trade (domestic/foreign).

Clients

Who paid to be heard, by how many filings named the bill.

ClientBusinessStateFirmsFilingsReported
AMERICAN GAS ASSOCIATIONDistrict of Columbia16
CHAMBER OF COMMERCE OF THE U.S.A.District of Columbia16
CENTERPOINT ENERGYIndiana15
CMS ENERGY CORPDistrict of Columbia15
INDEPENDENT PETROLEUM ASSOCIATION OF AMERICADistrict of Columbia15
XCEL ENERGY INCDistrict of Columbia15
ENBRIDGE (U.S.) INCTexas14
INTERSTATE NATURAL GAS ASSOCIATION OF AMERICADistrict of Columbia14
AMERICAN PIPELINE CONTRACTORS ASSOCIATIONTrade association representing contractors and suppliers in pipeline constructionMaryland13$240K
APPALACHIAN VOICESEnvironmental and economic development nonprofitVirginia13
CHEVRON U.S.A. INC.California13
COMPTEL DBA INCOMPASDistrict of Columbia13
PUGET SOUND ENERGYWashington13
POWER & COMMUNICATION CONTRACTORS ASSOCIATIONTrade association representing contractors and suppliers involved in utility constructionMaryland11$50K
AMERICAN EXPLORATION & PRODUCTION COUNCILDistrict of Columbia11
AMERICAN PETROLEUM INSTITUTEDistrict of Columbia11
LEAGUE OF CONSERVATION VOTERSDistrict of Columbia11

Firms

Registrants who filed on the bill, by filings.

Lobbyists

Named on the filings that cite the bill. The 20 named most often, of 168.

Filings

The documents themselves, on the Senate’s Lobbying Disclosure site, largest reported first.

ClientRegistrantPeriodReportedDocument
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2026 first_quarter$19.8M1st Quarter - Amendme…
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2026 first_quarter$19.8M1st Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2025 second_quarter$19.3M2nd Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2025 fourth_quarter$18M4th Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2026 second_quarter$17M2nd Quarter - Report
CHAMBER OF COMMERCE OF THE U.S.A.CHAMBER OF COMMERCE OF THE U.S.A.2025 third_quarter$13.7M3rd Quarter - Report
AMERICAN PETROLEUM INSTITUTEAMERICAN PETROLEUM INSTITUTE2025 fourth_quarter$1.9M4th Quarter - Report
CHEVRON U.S.A. INC.CHEVRON U.S.A. INC.2025 fourth_quarter$1.9M4th Quarter - Report
CHEVRON U.S.A. INC.CHEVRON U.S.A. INC.2026 second_quarter$1.7M2nd Quarter - Report
CHEVRON U.S.A. INC.CHEVRON U.S.A. INC.2026 first_quarter$1.6M1st Quarter - Report
XCEL ENERGY INCXCEL ENERGY, INC2026 first_quarter$960K1st Quarter - Report
AMERICAN EXPLORATION & PRODUCTION COUNCILAMERICAN EXPLORATION & PRODUCTION COUNCIL2025 fourth_quarter$700K4th Quarter - Report
XCEL ENERGY INCXCEL ENERGY, INC2025 second_quarter$560K2nd Quarter - Report
ENBRIDGE (U.S.) INCENBRIDGE (U.S.) INC2026 second_quarter$412K2nd Quarter - Report
ENBRIDGE (U.S.) INCENBRIDGE (U.S.) INC2026 first_quarter$412K1st Quarter - Report
PUGET SOUND ENERGYPUGET SOUND ENERGY2025 fourth_quarter$400K4th Quarter - Report
XCEL ENERGY INCXCEL ENERGY, INC2025 third_quarter$400K3rd Quarter - Report
XCEL ENERGY INCXCEL ENERGY, INC2025 fourth_quarter$380K4th Quarter - Report
XCEL ENERGY INCXCEL ENERGY, INC2026 second_quarter$370K2nd Quarter - Report
CMS ENERGY CORPCMS ENERGY CORP2026 first_quarter$360K1st Quarter - Report

Classification

The Congressional Research Service files H.R. 3668 under Energy, one of its 31 policy areas, and gives it 11 legislative subjects.

CRS Subjects

CRS assigns every bill one policy area from its 31; H.R. 3668’s is Energy.

hr3668/policy-areas.txt
EnergyAgriculture and FoodAnimalsArmed Forces and National SecurityArts, Culture, ReligionCivil Rights and Liberties, Minority IssuesCommerceCongressCrime and Law EnforcementEconomics and Public FinanceEducationEmergency ManagementEnvironmental ProtectionFamiliesFinance and Financial SectorForeign Trade and International FinanceGovernment Operations and PoliticsHealthHousing and Community DevelopmentImmigrationInternational AffairsLabor and EmploymentLawNative AmericansPublic Lands and Natural ResourcesScience, Technology, CommunicationsSocial WelfareSports and RecreationTaxationTransportation and Public WorksWater Resources Development

Legislative Subjects

H.R. 3668 carries 11 of CRS’s legislative subjects, from Computer security and identity theft to Transportation safety and security.

hr3668/subjects.txt
Computer security and identity theftEnvironmental assessment, monitoring, researchFederal Energy Regulatory Commission (FERC)Government information and archivesIntergovernmental relationsLicensing and registrationsOil and gasPipelinesState and local government operationsTransportation employeesTransportation safety and security

Constitutional authority

The clause the sponsor cites as Congress’s power to enact H.R. 3668, as entered in the Congressional Record.

[Congressional Record Volume 171, Number 93 (Monday, June 2, 2025)][House]From the Congressional Record Online through the Government Publishing Office [www.gpo.gov]By Mr. HUDSON:H.R. 3668.Congress has the power to enact this legislation pursuantto the following:Section 8 of Article I of the Constitution[Page H2382]

Source: congress.gov · legiscan.com